1962 as first step to the paper industry complex, the straw pulp mill began its operation
1966 the first run of PM 1
1967 the first run of PM 2
1976 the first run of PM 3 for brown paper the corrugator went into operation, with this step the paper industry complex became complete
1990 foundation of Dunapack Ltd, ownership structure: 60% Hungarian State, 40% Prinzhorn Group
1995 the Prinzhorn Group gained full ownership in Dunapack Ltd
2007 Establishing Hamburger Hungaria Ltd, November 9th – laying the foundation stone of the new paper mill for PM 7
2008 October 14th – topping out ceremony of the new paper mill
2008 "Investors of the Year" award
2009 July – startup of PM7
2012 The 1st million tons of paper produced on PM7
2013 Receiving the Hungarian environmental award "Ökoindustra"
2014 February 19th - Prinzhorn Group Hungary is the first environmental company, that signs strategic partnership agreement with the Hungarian Government
2014 May 21st - Foundation stone laying ceremony of the power plant in Dunaújváros
2016 Juny 10th – Opening ceremony of the state - of - the - art Hamburger Hungaria Power Plant